Earned Value Management ( EVM ) - Important Terms , Definitions and Formulas

Earned Value Management ( EVM ) - Important Terms , Definitions and Formulas


1. Budget at completion (BAC) - The total authorized budget for the project.


2. Planned value (PV) - The budgeted amounts assigned to work planned to have been  completed.


   Formula : PV = BAC × (time passed ÷ total schedule time)


3. Earned value (EV) - The value of completed work, expressed in terms of the budget assigned to that work.


    Formula : EV = BAC × (work completed ÷ total work required)


4. Schedule variance (SV) - The difference between earned value and planned value. This value indicates whether  project work is proceeding as planned in the schedule.


   Formula : SV = EV – PV


5. Cost variance (CV) - The difference between earned value and actual costs.


   Formula : CV = EV – AC


6. Schedule performance index (SPI) - The ratio between earned value and planned value, which represents schedule performance. An SPI of one indicates the project is on schedule. A value greater than one indicates it is ahead of schedule, and a value less than one indicates it is behind schedule.


 Formula : SPI = EV ÷ PV



7. Cost performance index (CPI) - The ratio between earned value and actual costs, which represents cost performance. A CPI value greater than one indicates better performance than expected, whereas a value less than one indicates poor performance.


 Formula : CPI = EV ÷ AC


No comments:

Post a Comment

Labels

.NET Framework Interview Questions (7) .NET Interview Questions (10) .NET Remoting Interview Questions (1) ADO.NET and BLOB Error (1) ADO.NET Interview Questions (4) Agile Articles (9) AJAX Articles (5) AJAX Interview Questions (11) Algorithms (2) Analytics Articles (2) Analytics Interview Questions (3) Android FAQs - Part 1 (2) Articles (13) ASP.NET Articles (24) ASP.NET Error and Resolution (4) ASP.NET Interview Questions (23) ASP.NET Tutorial (8) AWS Interview Questions (16) Business Analyst Interview Questions (1) Cloud Computing Interview Questions (16) CSharp Articles (17) CSharp Interview Questions (32) CSharp Tutorial (17) Data Analysis (2) Data Structure (1) Design Pattern Articles (5) DevOps Tutorial (1) Digital Marketing Interview Questions (1) Download Templates (1) Error Resolution (6) Excel Articles (9) Excel Macros (1) Excel Tips and Tricks (10) HTML5 Interview Questions (3) HTML5 Tutorial (3) Interview Preparation (2) Interview Questions (24) Introduction to Business Analytics (10) Introduction to Python (7) Introduction to R Programming (23) JAVA Articles (6) Java Tutorial (5) LINQ Articles (4) LINQ Interview Questions (2) LINQ Tutorial (3) Microservices Interview Questions (1) MVCInterviewQuestions (2) OOPs Interview Questions (4) Oracle 9i Tutorial (14) Oracle Articles (2) Oracle Interview Questions (15) Outlook Error (1) PHP Interview Questions (3) PHP Tutorial (3) Product Management (12) Product Management Interview Questions (14) Product Owner Interview Questions (2) Program Management (5) Project Management (13) Project Management Articles (34) Project Management Interview Questions (25) Quiz (1) RallyDev Help (1) Scrum Master Interview Questions (11) Selenium Tutorial (1) Sharepoint Articles (1) SQL Interview Questions (23) SQL Server Articles (20) SSIS Interview Questions (6) SSRS Interview Questions (1) Technical Program Management (12) Technical Program Management - Interview Questions (24) TechnicalProgramManagement (5) Threading Interview Questions (2) Tutorial (8) UML Articles (3) UML Interview Questions (2) Unix (3) UNIX Tutorial (3) WCF Articles (20) WCF Interview Questions (9) WCF Quiz (2) WCF Tutorial (16) Web Service Articles (5) Web Service Interview Questions (3) Window Azure (1) XML Articles (6) XML Interview Questions (3) XML Tutorial (3)