Question 1.
What are number of communication channels possible in a project with Team size of 8
Answer 1 .
If n is the number of people in project, then there are n(n-1)/2 communication channels in the project
Hence Answer is 8(8-1)/2 = 28
Question 2.
What is Parametric estimating ?
Answer 2.
Parametric estimating is the process of using historical data to compare against your project to determine a correlation and thereby a cost estimate for your current project
Question 3.
What is output of Plan Quality process ?
Answer 3.
Outputs of Plan Quality process includes :
What are number of communication channels possible in a project with Team size of 8
If n is the number of people in project, then there are n(n-1)/2 communication channels in the project
Hence Answer is 8(8-1)/2 = 28
What is Parametric estimating ?
Parametric estimating is the process of using historical data to compare against your project to determine a correlation and thereby a cost estimate for your current project
Question 3.
What is output of Plan Quality process ?
Answer 3.
Outputs of Plan Quality process includes :
- Quality Management Plan
- Quality Metrics
- Quality Checklists
- Process Improvement Plan
- Project Document Updates
No comments: